Project Timeline

Track and manage your project schedule

Project Timeline
Apr 1, 2025 - Jun 21, 2025
Task
Apr 1 - Apr 7
Apr 8 - Apr 14
Apr 15 - Apr 21
Apr 22 - Apr 28
Apr 29 - May 5
May 6 - May 12
May 13 - May 19
May 20 - May 26
May 27 - Jun 2
Jun 3 - Jun 9
Jun 10 - Jun 16
Jun 17 - Jun 21
Project Planning
Apr 1, 2025 - Apr 7, 2025
Permits & Approvals
Apr 5, 2025 - Apr 15, 2025
Permits & Approvals
Demolition
Apr 16, 2025 - Apr 20, 2025
Framing
Apr 21, 2025 - Apr 28, 2025
Plumbing Rough-In
Apr 29, 2025 - May 5, 2025
Electrical Rough-In
May 1, 2025 - May 7, 2025
HVAC Installation
May 3, 2025 - May 9, 2025
Insulation
May 10, 2025 - May 12, 2025
Drywall
May 13, 2025 - May 20, 2025
Painting
May 21, 2025 - May 27, 2025
Flooring Installation
May 28, 2025 - Jun 3, 2025
Cabinet Installation
Jun 4, 2025 - Jun 10, 2025
Countertop Installation
Jun 11, 2025 - Jun 13, 2025
Fixture Installation
Jun 14, 2025 - Jun 18, 2025
Final Inspection
Jun 19, 2025 - Jun 20, 2025
Completed
In Progress
Pending
Delayed