Change Orders

Manage project scope and budget changes

Original Budget
$45,000

Base contract amount

Approved Changes
$-570

2 approved changes

Pending Changes
+$285

1 pending approval

Adjusted Budget
$44,430

-1.3% change

Add Kitchen Island Electrical Upgrade

approved
addition

Client requested additional GFCI outlets and USB charging ports in the kitchen island.

ID:CO-001
Reason:Client Request
Submitted:2024-01-18
By:Project Manager
Schedule:+1 day
Budget:+$180
Scope:Electrical work expanded
+$180

+3h labor

Upgrade Countertop Edge Profile

pending
change

Change from standard straight edge to premium ogee edge profile on quartz countertops.

ID:CO-002
Reason:Design Change
Submitted:2024-02-01
By:Designer
Schedule:No change
Budget:+$285
Scope:Countertop fabrication updated
+$285

+2h labor

Remove Under-Cabinet Wine Rack

approved
deletion

Client decided to remove the planned under-cabinet wine rack to maximize storage space.

ID:CO-003
Reason:Client Request
Submitted:2024-01-25
By:Client
Schedule:-0.5 days
Budget:-$750
Scope:Cabinet configuration simplified
$-750

-4h labor

Add Tile Backsplash Extension

draft
addition

Extend subway tile backsplash to cover full wall behind stove instead of standard height.

ID:CO-004
Reason:Design Enhancement
Submitted:Not submitted
By:Project Manager
Schedule:+1 day
Budget:+$420
Scope:Backsplash area increased
+$420

+6h labor