Back to Project

Project Timeline

Track milestones and manage project schedule

Overall Progress
50%

3 of 6 milestones completed

Current Milestone
Cabinet Installation

75% complete

Next Up
Countertop Installation

Starts 2024-02-08

Project End Date
Feb 17

On schedule

Project Planning & Permits

completed

Finalize design plans, obtain necessary permits, and order initial materials

2024-01-10 - 2024-01-14
Project Manager
Completed 2024-01-14

Tasks (3/3)

Submit permit applications2024-01-12
Finalize material orders2024-01-14
Schedule inspections2024-01-14

Notes

All permits approved on schedule. No delays.

Demolition & Site Preparation

completed

Remove existing fixtures, cabinets, and prepare space for new installation

2024-01-15 - 2024-01-17
Demolition Crew
Completed 2024-01-17

Tasks (3/3)

Remove old cabinets2024-01-15
Remove countertops2024-01-16
Clean and prep walls2024-01-17

Notes

Demolition completed without issues. Found some minor electrical work needed.

Electrical & Plumbing Rough-in

completed

Install new electrical circuits, outlets, and update plumbing for island

2024-01-20 - 2024-01-26
Licensed Electrician & Plumber
Completed 2024-01-26

Tasks (3/3)

Install new electrical circuits2024-01-22
Add island electrical2024-01-24
Update plumbing for island2024-01-26

Notes

Electrical inspection passed. Plumbing updated as planned.

Cabinet Installation

in progress
75% complete

Install base and upper cabinets, including hardware and adjustments

2024-02-01 - 2024-02-07
Cabinet Installation Team
In progress
Progress75%

Tasks (1/3)

Install base cabinets2024-02-03
Install upper cabinets2024-02-05
Install hardware and doors2024-02-07

Notes

Base cabinets completed. Working on uppers. On schedule.

Countertop Installation

pending

Template, fabricate, and install quartz countertops

2024-02-08 - 2024-02-12
Countertop Fabricator
Not started

Tasks (0/3)

Create template2024-02-08
Fabricate countertops2024-02-10
Install countertops2024-02-12

Notes

Waiting for cabinet completion before templating.

Backsplash & Final Details

pending

Install tile backsplash, lighting fixtures, and final touches

2024-02-13 - 2024-02-17
Tile Installer & Electrician
Not started

Tasks (0/3)

Install tile backsplash2024-02-15
Install light fixtures2024-02-16
Final cleanup and inspection2024-02-17

Notes

Final phase - all materials ready.